From Crate to Commissioning: Hardware, Technical Data and Commissioning Steps

From Crate to Commissioning: Hardware, Technical Data and Commissioning Steps
The design numbers you need, and the checklist to follow before the relay faces its first real fault.
Part 10 of 10⏱ 4 min readLevel: Intermediate
🎯 What you will learn in this part
  • Mounting versions and housing sizes
  • Numbers for inputs, supply and outputs
  • Commissioning and maintenance steps

Three mounting versions

VersionNotes
Flush / cubicle mounting7XP20 housing in sizes 1/3, 1/2 and 1/1, for a panel or rack.
Surface mountingThe same sizes in a heavier housing.
Detached operator panelThe 7SA64: the device in a 1/2 or 1/1 housing with a detached operator panel.
Approximate weightFlushSurface
1/3 (7SA61)5 kg9.5 kg
1/26 kg11 kg
1/110 kg19 kg

Degree of protection: IP 51 at the front and IP 50 at the rear for the flush case (IP 51 for the surface case), and IP 2x for personal safety with the cover closed.

Measuring inputs and supply

ItemValue
Nominal frequency50 or 60 Hz (adjustable)
Nominal current IN1 A or 5 A
Current input burdenAbout 0.05 VA (1 A) / 0.3 VA (5 A)
Current overload capability500 A for 1 s, 150 A for 10 s, 20 A continuous, dynamic 1250 A (half cycle)
Nominal voltage80 to 125 V; burden 0.1 VA or less; 230 V continuous
DC supply24/48 (19–58), 60/110/125 (48–150), 110/125/220/250 (88–300) V
AC supply115 V (92–132 V)
Power consumptionAbout 5 W quiescent, and 7 to 20 W energized depending on the version
Bridging of supply lossAt least 50 ms at 48 V DC and at 110 V or above, and 20 ms at 24 V and 60 V

Binary inputs and outputs

  • Inputs: from 5 to 33 allocatable inputs depending on the version; control voltage from 24 to 250 V DC in three ranges set by jumpers; about 1.8 mA; maximum permissible voltage 300 V DC.
  • Outputs: normal, fast, switch-selectable (NO/NC) and high-speed (power) relays, with operating times of about 8 ms for normal, 5 ms for fast and 1 ms for high-speed.
  • Making capacity of 1000 W/VA, 5 A continuous, 30 A for 0.5 s, and 250 V.
  • An independent live-status contact (NC or NO, selectable) to alarm that the device is out of service.
⚠️ Set the input thresholds
The binary input threshold jumpers must be set to the control voltage (24/48 V, 60/110/125 V or 220/250 V) before commissioning. A wrong setting can leave an input that does not pick up.

Optical interfaces for protection data

Modules FO5, FO6, FO7 and FO8 (see Part 6) are fitted at mounting location D on the rear of the device. Some are laser class 1 and some 3A per EN 60825, and the idle state is "light off".

Commissioning steps

  • 1. Test mode and transmission blocking: to avoid sending wrong signals to the system during testing.
  • 2. Check the system (SCADA) interface.
  • 3. Check the binary inputs and outputs: they can be displayed and set directly, which shortens wiring checks considerably.
  • 4. Check the analog outputs (if fitted).
  • 5. Check the communication topology between devices.
  • 6. Tests for the breaker failure protection.
  • 7. Current, voltage and phase rotation checks.
  • 8. Directional checks with load current.
  • 9. Polarity check of voltage input U4.
  • Then the circuit breaker trip test and the final preparation of the device.

After commissioning, the manual recommends routine checks and maintenance, and procedures for troubleshooting, repair and return (Chapter 9).

✅ Key Takeaways
  • Three mounting versions: flush, surface and detached operator panel, in sizes 1/3, 1/2 and 1/1.
  • IN of 1 or 5 A, voltage 80–125 V, and DC or AC supply in several ranges.
  • From 5 to 33 binary inputs, with thresholds set by jumpers.
  • Commissioning starts with test mode and transmission blocking and ends with directional checks under load.
🧠 Test yourself (click a question to reveal the answer)
Which housing sizes are available?
1/3, 1/2 and 1/1 (depending on the model).
What binary input voltages are supported?
24 to 250 V DC in three ranges, with a maximum of 300 V DC.
What is the first commissioning step?
Test mode and transmission blocking.
Source: Siemens manual "SIPROTEC Distance Protection 7SA6" (C53000-G1176-C156, Siemens copyright 2000 and 2002). This article is an educational explanation in the author's own words; values are for guidance only, so check the manual for your installed version before any design or setting. This blog is not affiliated with Siemens. SIPROTEC and DIGSI are trademarks of their owners.